Harrisburg University Health Science Education Center: Structural Steel Fabrication Success

by | News

Offering space for 1,000 new students in health sciences and advanced manufacturing is the new $100-million, 260,000-square-foot Health Science Education Center at Harrisburg University of Science and Technology. Kinsley’s Steel division supplied 2,800 tons of structural steel and 2,400 squares of metal decking for this 11-story building at the corner of South Third and Chestnut Streets in downtown Harrisburg, Pennsylvania.

Project Overview

The Health Science Education Center at Harrisburg University of Science and Technology is a $100 million, 260,000 sq ft building designed to house 1,000 students in health sciences and advanced manufacturing. Kinsley Steel supplied 2,800 tons of structural steel and 2,400 squares of metal decking for this state-of-the-art facility. Despite COVID-related setbacks and design changes, our team kept the project moving forward with efficiency and precision.

 

 

 

 

Facing Fabrication & Detailing Challenges

With design adjustments occurring on an almost weekly basis, flexibility became essential. Our detailing team continuously updated shop drawings to reflect revisions, while our purchasing department worked diligently to secure materials amid supply chain challenges. As Project Manager Glen Williams shared, “Our purchasing department is resourceful... They know how to get what we need when we need it.”

Creative purchasing solutions, the use of stockhouses, and careful rolling schedules ensured the fabrication shop had what it needed. Hold–release cycles were managed to keep steel flowing without overwhelming the schedule, balancing speed with accuracy.

Erection Strategy on a Tight Site

The erection phase demanded careful planning due to a confined urban site and complex building features. Some highlights included:

  • A 17-ft-tall steel “eyebrow” truss installed with precision
  • Custom “W” shapes designed for unique structural requirements
  • Two-story atriums requiring special sequencing strategies

Through Tekla 3D modeling, the team implemented a three-story erection sequence that reduced field rework and streamlined construction. The result was safer, more efficient steel placement in challenging conditions.

Team Effort in Action

Our field crews worked long hours in extreme summer heat, demonstrating resilience and commitment. Constant communication between office and field teams was key to handling adjustments quickly and safely. The result? Steel erection was completed three weeks ahead of schedule, keeping the overall project on pace for its targeted 2023 opening.

Takeaway – Engineering Resilience in Steel

This project is a showcase of Kinsley Steel’s adaptability, teamwork, and engineering expertise. By overcoming pandemic disruptions, design changes, and jobsite constraints, our team delivered a structural steel success story that will serve Harrisburg University’s growing community for decades to come.